项目| 文件编号 | 3329 | 工期 | 1126天 | 开始时间 | 2014-04-01 | 结束时间 | 2017-04-30 |
| 任务数 | 59K | 整理日期 | 2019/5/17 | 下载次数 | 3931次 | ||
| 下载地址 | 计划文件点击下载(登录后才可以下载) | ||||||
| 项目 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
编号 |
任务名称 |
工期 |
| 1 | Improvement of PR314D |
1080天 |
| 2 | Mobilization & Preliminary |
92天 |
| 3 | Mobilization |
92天 |
| 4 | Main Camp for contractor and Eng |
61天 |
| 5 | Crushing Plant and Mixing Plant |
61天 |
| 6 | Maintenace of Road &Bridge |
1080天 |
| 7 | Maintenace of Road &Bridge |
1080天 |
| 8 | Embankment & sub-grade |
762天 |
| 9 | K62+430-K45+000 |
151天 |
| 10 | K45+000-K21+000 |
212天 |
| 11 | K21+000-K0+000 |
152天 |
| 12 | Pavement |
851天 |
| 13 | sub-base course |
609天 |
| 14 | base course |
549天 |
| 15 | DBSJ |
577天 |
| 16 | Structures |
212天 |
| 17 | Box Culvert-1 |
488天 |
| 18 | K55+350Box Culvert |
31天 |
| 19 | K60+925Box Culvert |
31天 |
| 20 | K61+100Box Culvert |
30天 |
| 21 | K62+031Box Culvert |
31天 |
| 22 | Precasting-1 |
62天 |
| 23 | Precasting piles&Voied Plank |
62天 |
| 24 | Bridge K54+706 |
123天 |
| 25 | Cofferdam &Excavation |
31天 |
| 26 | Driven Piles |
31天 |
| 27 | Abutment pier & Bent Beam |
30天 |
| 28 | Install Voied Plank |
10天 |
| 29 | Top Slab |
21天 |
| 30 | Bridge K54+706 |
123天 |
| 31 | Cofferdam &Excavation |
31天 |
| 32 | Driven Piles |
31天 |
| 33 | Abutment pier & Bent Beam |
30天 |
| 34 | Install Voied Plank |
10天 |
| 35 | Top Slab |
21天 |
| 36 | Precasting-2 |
122天 |
| 37 | Precasting piles&Voied Plank |
122天 |
| 38 | Bridge K24+267 |
183天 |
| 39 | Cofferdam &Excavation |
30天 |
| 40 | Driven Piles |
52天 |
| 41 | Abutment pier & Bent Beam |
61天 |
| 42 | Install Voied Plank |
20天 |
| 43 | Top Slab |
41天 |
| 44 | Bridge K24+267 |
153天 |
| 45 | Cofferdam &Excavation |
31天 |
| 46 | Driven Piles |
30天 |
| 47 | Abutment pier & Bent Beam |
51天 |
| 48 | Install Voied Plank |
11天 |
| 49 | Top Slab |
30天 |
| 50 | Box Culvert-2 |
31天 |
| 51 | K28+586 Box Culvert |
31天 |
| 52 | Drainage & protection works |
748天 |
| 53 | K62+430-K45+000 |
151天 |
| 54 | K45+000-K21+000 |
212天 |
| 55 | K21+000-K0+000 |
152天 |
| 56 | Road Furniture |
409天 |
| 57 | Road Furniture |
409天 |
| 58 | Take over |
0天 |
| 59 | Take over |
0天 |