文件编号 | 3230 | 工期 | 665天 | 开始时间 | 2015-04-08 | 结束时间 | 2017-06-25 |
任务数 | 34K | 整理日期 | 2019/5/17 | 下载次数 | 3894次 | ||
下载地址 | 计划文件点击下载(登录后才可以下载) |
20161208-1 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
编号 |
任务名称 |
工期 |
开始时间 |
结束时间 |
前置任务 |
资源名称 |
1 | New Project |
665天 | 2015-04-08 | 2017-06-25 | ||
2 | 2015 |
424天 | 2015-04-08 | 2016-08-16 | ||
3 | commmencement date |
0天 | 2015-04-08 | 2015-04-08 | ||
4 | Handing over of construction site |
7天 | 2015-04-08 | 2015-04-14 | 3 | |
5 | Approval of working drawings by the Engineer |
214天 | 2015-04-08 | 2015-11-07 | 3[SS] | |
6 | Removal of top soil |
360天 | 2015-04-08 | 2016-06-13 | ||
7 | milling of original asphalt pavement |
360天 | 2015-04-11 | 2016-06-16 | 6[SS+3] | |
8 | Removal of Monolithic material(lean concrete) |
360天 | 2015-04-16 | 2016-06-21 | 7[SS+4] | |
9 | Culvert 367+40-694+00(RHS) |
202天 | 2015-04-16 | 2015-11-03 | 8[SS] | |
10 | Bridge at PK446+56 |
80天 | 2015-04-08 | 2015-06-26 | ||
11 | Bridge at PK505+53 |
83天 | 2015-04-08 | 2015-06-29 | 10[SS] | |
12 | Bridge at PK543+43 |
56天 | 2015-05-08 | 2015-07-02 | 11[SS+30] | |
13 | Bridge at PK608+55 |
112天 | 2015-07-15 | 2015-11-03 | 12[FS+12] | |
14 | Subgrade PK367+40-694+00(RHS) |
232天 | 2015-04-18 | 2015-12-05 | 8[SS+2] | |
15 | 不良地基处理 |
168天 | 2015-12-06 | 2016-08-02 | 14 | |
16 | Subbase PK367+40-694+00(RHS) |
390天 | 2015-04-28 | 2016-08-02 | 15[FF],14[SS+10] | |
17 | base course PK367+40-694+00(RHS) |
380天 | 2015-05-18 | 2016-08-12 | 16[SS+20] | |
18 | concrete top course PK367+40-694+00(RHS) |
363天 | 2015-06-07 | 2016-08-15 | 17[SS+20] | |
19 | Completion of single carriageway 32km |
0天 | 2016-08-16 | 2016-08-16 | 18[FF],3[SF+424] | |
20 | 2016 |
665天 | 2015-04-08 | 2017-06-25 | ||
21 | Bridge at PK621+92 |
277天 | 2015-04-08 | 2016-03-22 | ||
22 | Bridge at PK636+38 |
315天 | 2015-04-12 | 2016-05-03 | 21[SS+4] | |
23 | Bridge at PK663+48 |
265天 | 2015-04-12 | 2016-03-14 | 22[SS] | |
24 | Bridge at PK610+65 |
327天 | 2015-04-28 | 2016-05-31 | 21[SS+20] | |
25 | Culvert 367+40-694+00(LHS) |
207天 | 2015-11-04 | 2016-08-09 | 9 | |
26 | Lean concrete |
29天 | 2015-08-16 | 2015-09-13 | 18[SS+70] | |
27 | Subgrade PK367+40-694+00(LHS) |
441天 | 2015-09-14 | 2017-04-21 | 26 | |
28 | Subbase PK367+40-694+00(LHS) |
441天 | 2015-09-24 | 2017-05-01 | 26[FS+10],27[FF+10] | |
29 | base course PK367+40-694+00(LHS) |
441天 | 2015-10-04 | 2017-05-11 | 26[FS+20],28[FF+10] | |
30 | concrete top course PK367+40-694+00(LHS) |
205天 | 2016-08-18 | 2017-05-21 | 29[FF+10],18 | |
31 | Subsidiary facilities |
180天 | 2016-09-25 | 2017-06-03 | 18[FS+40] | |
32 | Site clearance |
30天 | 2017-05-20 | 2017-06-18 | 30[FF+28] | |
33 | Acceptance |
7天 | 2017-06-19 | 2017-06-25 | 32 | |
34 | Taking-over |
0天 | 2017-06-25 | 2017-06-25 | 19[FF+239],33[FF] |