文件编号 | 2172 | 工期 | 269天 | 开始时间 | 2016-11-05 | 结束时间 | 2017-11-15 |
任务数 | 45K | 整理日期 | 2019/5/17 | 下载次数 | 3950次 | ||
下载地址 | 计划文件点击下载(登录后才可以下载) |
项目1111 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
编号 |
任务名称 |
工期 |
开始时间 |
结束时间 |
前置任务 |
资源名称 |
1 | Fence |
56天 | 2016-11-05 | 2017-01-20 | ||
2 | Leveling and grading |
51天 | 2016-11-15 | 2017-01-24 | 1[SS] | |
3 | Measurement positioning |
3天 | 2016-12-06 | 2016-12-08 | ||
4 | Underground part of the construction |
46天 | 2016-12-09 | 2017-02-10 | 1[SS],3 | |
5 | The ground part |
75天 | 2017-02-13 | 2017-05-26 | 4 | |
6 | decoration |
30天 | 2017-05-29 | 2017-07-07 | 5 | |
7 | Positioning and excavation |
7天 | 2017-05-05 | 2017-05-15 | 5[SS] | |
8 | Pipeline laying and inspection well construction |
23天 | 2017-05-16 | 2017-06-15 | 7 | |
9 | Backfill compaction |
5天 | 2017-06-16 | 2017-06-22 | 8 | |
10 | Positioning and excavation |
7天 | 2017-05-05 | 2017-05-15 | 4 | |
11 | Steel banding and support mode |
20天 | 2017-05-16 | 2017-06-12 | 10 | |
12 | Concrete pouring |
2天 | 2017-06-13 | 2017-06-14 | 11 | |
13 | Conservation and backfill compact |
6天 | 2017-06-15 | 2017-06-22 | 12 | |
14 | Positioning and excavation |
16天 | 2016-12-20 | 2017-01-10 | 1[SS] | |
15 | Steel banding and support mode |
86天 | 2017-01-11 | 2017-05-10 | 14 | |
16 | Concrete pouring |
3天 | 2017-05-11 | 2017-05-15 | 15 | |
17 | Conservation and backfill compact |
13天 | 2017-05-16 | 2017-06-01 | 16 | |
18 | Frame installation |
27天 | 2017-06-02 | 2017-07-10 | 17 | |
19 | Measurement positioning |
2天 | 2017-05-22 | 2017-05-23 | ||
20 | Foundation construction |
17天 | 2017-05-24 | 2017-06-15 | 15,19 | |
21 | Lightning rod installation |
17天 | 2017-06-16 | 2017-07-10 | 20 | |
22 | Foundation construction |
5天 | 2017-05-30 | 2017-06-05 | 15 | |
23 | Bracket installation |
11天 | 2017-06-06 | 2017-06-20 | 22 | |
24 | Device installation |
16天 | 2017-06-21 | 2017-07-12 | 23 | |
25 | Ancillary works construction |
44天 | 2017-05-11 | 2017-07-11 | 15 | |
26 | Measurement positioning |
36天 | 2016-11-22 | 2017-01-10 | 1[SS] | |
27 | Road cleaning |
39天 | 2016-11-24 | 2017-01-17 | 1[SS] | |
28 | Compaction molding |
47天 | 2016-11-26 | 2017-01-31 | 1[SS] | |
29 | Road surface laying |
15天 | 2017-08-01 | 2017-08-21 | 30 | |
30 | Positioning and excavation |
111天 | 2017-02-01 | 2017-07-05 | 28 | |
31 | Wire laying and connection |
111天 | 2017-02-06 | 2017-07-10 | 1 | |
32 | Backfill compaction |
117天 | 2017-02-08 | 2017-07-20 | 28 | |
33 | Positioning and excavation |
111天 | 2017-02-01 | 2017-07-05 | 28 | |
34 | Cabling |
111天 | 2017-02-06 | 2017-07-10 | 28 | |
35 | Backfill compaction |
117天 | 2017-02-08 | 2017-07-20 | 28 | |
36 | Measurement positioning |
86天 | 2017-01-16 | 2017-05-15 | 26 | |
37 | Drilling |
108天 | 2017-01-20 | 2017-06-20 | 36[SS] | |
38 | Concrete pouring |
119天 | 2017-01-25 | 2017-07-10 | 36[SS] | |
39 | Tracking bracket installation |
122天 | 2017-02-10 | 2017-07-31 | 38[SS] | |
40 | Panel Installation |
110天 | 2017-03-10 | 2017-08-10 | 39[SS] | |
41 | Combiner box foundation construction and equipment |
109天 | 2017-02-20 | 2017-07-20 | 38[SS] | |
42 | Transformer foundation |
41天 | 2017-05-15 | 2017-07-10 | 41[SS] | |
43 | Inverter founation |
41天 | 2017-05-15 | 2017-07-10 | 42[SS] | |
44 | Slope protection |
42天 | 2017-07-11 | 2017-09-06 | 31 | |
45 | PUNCH LIST CLOSE |
50天 | 2017-09-07 | 2017-11-15 | 44 |