文件编号 20218 工期 104天 开始时间 2018-11-10 结束时间 2019-02-21
任务数 49K 整理日期 2019/5/18 下载次数 4059次
下载地址 计划文件点击下载(登录后才可以下载)
计划内容
项目

编号

任务名称

开始时间

结束时间

1
Preparation before construction
2018 November 10 2018 November 16
2
Insepectinon of trestle foundation
2018 November 17 2018 November 18
3
T1 Transfer statinon Installation
2018 November 17 2018 November 24
4
No.1 trestle 1~38 shaft installation
2018 November 17 2018 November 28
5
No.2 trestle 1 span assenbly
2018 November 29 2018 December 4
6
Assembly lf the first span bracket
2018 December 5 2018 December 6
7
The third Span Assembly of No.2 trestle
2018 December 7 2018 December 14
8
The fourth span assembly of No.2 trestle bridge
2018 December 7 2018 December 14
9
Installation of the first span bracket
2018 December 7 2018 December 7
10
The first Span installation and correction of the trestle
2018 December 8 2018 December 9
11
The second span assembly of No.2 trestle
2018 December 8 2018 December 14
12
Assembly of the second span bracket
2018 December 15 2018 December 17
13
Assembly of the third span bracket
2018 December 15 2018 December 19
14
Assembly of the fourth span bracket
2018 December 15 2018 December 19
15
Installation of the second span brackt
2018 December 18 2018 December 19
16
The second Span installation and Correction of No.2 trestle
2018 December 20 2018 December 21
17
Installation of No.2 trestle 1,2 span pattern steel plate
2018 December 22 2018 December 31
18
Installation of the third span bracket
2018 December 22 2018 December 23
19
Installatin of the fourth span bracket
2018 December 24 2018 December 25
20
The third Span Installation and Correction of No.2 trestle
2018 December 26 2018 December 27
21
The fourth Span Installation and Correction of No.2 trestle
2018 December 28 2018 December 29
22
The fifth span assembly of No.2 trestle
2018 December 30 2019 January 6
23
Installatino of trestle 3 and 4 span steel plate
2018 December 24 2019 January 4
24
The sixth span assembly of No.2 trestle
2018 December 30 2019 January 7
25
No.1 trestle construction preparation
2018 December 24 2018 December 28
26
No.1 trestle installation
2018 December 28 2019 February 8
27
The fifth span bracket assembly
2018 December 24 2018 December 30
28
The sixth span bracket assembly
2018 December 26 2019 January 3
29
Installation of the fifth span bracket
2018 December 31 2019 January 2
30
Installation of the sixth span bracket
2019 January 4 2019 January 6
31
The fifth Installation and correction of No.2 trestle
2019 January 7 2019 January 8
32
The sixth Installation and correction of No.2 trestle
2019 January 8 2019 January 12
33
The seventh assembly of No.2 trestle
2019 January 8 2019 January 16
34
The eighth span assemly of No.2 trestle
2019 January 8 2019 January 16
35
Installation of No.2 trestle 5and6 Pattern Stell Plate
2019 January 5 2019 January 17
36
The seventh span bracket assembly
2018 December 31 2019 January 7
37
The eighth span bracket assembly
2019 January 4 2019 January 12
38
Installation and Correction of the seventh span bracket
2019 January 13 2019 January 15
39
Installation and Correction of the eighth span bracket
2019 January 16 2019 January 18
40
Installation of steel support stair platform
2019 January 19 2019 January 28
41
Installation and Correction of 7th and 8th span No.2 trestle
2019 January 19 2019 January 23
42
Installation of 7th and 8th span No.2 trestle
2019 January 18 2019 January 30
43
The ninth and tenth of assembly of No.2 trestle
2019 January 24 2019 February 2
44
The ninth and tenth span assembly
2019 January 19 2019 January 27
45
The ninth and tenth bracket installation
2019 January 28 2019 February 1
46
The ninth and tenth installation of No.2 trestle
2019 February 2 2019 February 7
47
Installation of ninth and tenth pattern steel plate
2019 January 31 2019 February 10
48
第11跨拼装
2019 February 8 2019 February 16
49
第11跨花纹钢板安装
2019 February 17 2019 February 21