
| 文件编号 | 13901 | 工期 | 64天 | 开始时间 | 2017-09-01 | 结束时间 | 2017-11-03 |
| 任务数 | 231K | 整理日期 | 2019/5/17 | 下载次数 | 3898次 | ||
| 下载地址 | 计划文件点击下载(登录后才可以下载) | ||||||
编号 |
任务名称 |
工期 |
开始时间 |
结束时间 |
前置任务 |
资源名称 |
| 1 | 桩基1 |
9天 | 2017-09-01 | 2017-09-09 | ||
| 2 | 桩基2 |
9天 | 2017-09-10 | 2017-09-18 | 1 | |
| 3 | 桩基3 |
9天 | 2017-09-19 | 2017-09-27 | 2 | |
| 4 | 土方1 |
1天 | 2017-09-10 | 2017-09-10 | 1 | |
| 5 | 土方2 |
1天 | 2017-09-19 | 2017-09-19 | 2 | |
| 6 | 土方3 |
1天 | 2017-09-28 | 2017-09-28 | 3 | |
| 7 | 垫层+砍桩1 |
2天 | 2017-09-17 | 2017-09-18 | 4 | |
| 8 | 垫层+砍桩2 |
2天 | 2017-10-02 | 2017-10-03 | 5 | |
| 9 | 垫层+砍桩3 |
2天 | 2017-10-17 | 2017-10-18 | 6 | |
| 10 | 基础模板安装1 |
4天 | 2017-09-20 | 2017-09-23 | 7 | |
| 11 | 基础模板安装2 |
4天 | 2017-10-05 | 2017-10-08 | 8 | |
| 12 | 基础模板安装3 |
4天 | 2017-10-20 | 2017-10-23 | 9,17 | |
| 13 | 基础钢筋1 |
4天 | 2017-09-24 | 2017-09-27 | 10 | |
| 14 | 基础钢筋2 |
4天 | 2017-10-09 | 2017-10-12 | 25,11 | |
| 15 | 基础钢筋3 |
4天 | 2017-10-24 | 2017-10-27 | 12 | |
| 16 | 基混1 |
1天 | 2017-09-28 | 2017-09-28 | 13 | |
| 17 | 基混2 |
1天 | 2017-10-13 | 2017-10-13 | 14 | |
| 18 | 基混3 |
1天 | 2017-10-28 | 2017-10-28 | 15 | |
| 19 | 基础拆模1 |
2天 | 2017-09-29 | 2017-09-30 | 16 | |
| 20 | 基础拆模2 |
2天 | 2017-10-14 | 2017-10-15 | 17 | |
| 21 | 基础拆模3 |
2天 | 2017-10-29 | 2017-10-30 | 18 | |
| 22 | 回填土1 |
3天 | 2017-10-01 | 2017-10-03 | 19 | |
| 23 | 回填土2 |
3天 | 2017-10-16 | 2017-10-18 | 20 | |
| 24 | 回填土3 |
3天 | 2017-10-31 | 2017-11-02 | 21 | |
| 25 | 柱子钢筋1-1 |
1天 | 2017-10-04 | 2017-10-04 | 22 | |
| 26 | 柱子钢筋1-2 |
1天 | 2017-09-05 | 2017-09-05 | 100,71 | |
| 27 | 柱子钢筋1-3 |
1天 | 2017-09-05 | 2017-09-05 | 101 | |
| 28 | 柱子钢筋1-4 |
1天 | 2017-09-05 | 2017-09-05 | 102 | |
| 29 | 柱子钢筋1-5 |
1天 | 2017-09-06 | 2017-09-06 | 53 | |
| 30 | 柱子钢筋2-1 |
1天 | 2017-10-28 | 2017-10-28 | 23,100,15 | |
| 31 | 柱子钢筋2-2 |
1天 | 2017-09-05 | 2017-09-05 | 105 | |
| 32 | 柱子钢筋2-3 |
1天 | 2017-09-05 | 2017-09-05 | 115,106 | |
| 33 | 柱子钢筋2-4 |
1天 | 2017-09-05 | 2017-09-05 | 107,116 | |
| 34 | 柱子钢筋2-5 |
1天 | 2017-09-04 | 2017-09-04 | 117,74 | |
| 35 | 柱子钢筋3-1 |
1天 | 2017-11-03 | 2017-11-03 | 24 | |
| 36 | 柱子钢筋3-2 |
1天 | 2017-09-05 | 2017-09-05 | 116,110 | |
| 37 | 柱子钢筋3-3 |
1天 | 2017-09-03 | 2017-09-03 | 115 | |
| 38 | 柱子钢筋3-4 |
1天 | 2017-09-05 | 2017-09-05 | 112 | |
| 39 | 柱子钢筋3-5 |
1天 | 2017-09-03 | 2017-09-03 | 117 | |
| 40 | 柱梁板模板安装1-1 |
5天 | 2017-10-05 | 2017-10-09 | 25 | |
| 41 | 柱梁板模板安装1-2 |
5天 | 2017-09-06 | 2017-09-10 | 50 | |
| 42 | 柱梁板模板安装1-3 |
5天 | 2017-09-06 | 2017-09-10 | 27 | |
| 43 | 柱梁板模板安装1-4 |
5天 | 2017-09-06 | 2017-09-10 | 28 | |
| 44 | 柱梁板模板安装1-5 |
5天 | 2017-09-07 | 2017-09-11 | 29 | |
| 45 | 柱梁板模板安装2-1 |
5天 | 2017-10-29 | 2017-11-02 | 30 | |
| 46 | 柱梁板模板安装2-2 |
5天 | 2017-09-06 | 2017-09-10 | 31 | |
| 47 | 柱梁板模板安装2-3 |
5天 | 2017-09-06 | 2017-09-10 | 32 | |
| 48 | 柱梁板模板安装2-4 |
5天 | 2017-09-06 | 2017-09-10 | 33 | |
| 49 | 柱梁板模板安装2-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 50 | 柱梁板模板安装3-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 51 | 柱梁板模板安装3-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 52 | 柱梁板模板安装3-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 53 | 柱梁板模板安装3-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 54 | 柱梁板模板安装3-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 55 | 柱混凝土1-1 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 56 | 柱混凝土1-2 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 57 | 柱混凝土1-3 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 58 | 柱混凝土1-4 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 59 | 柱混凝土1-5 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 60 | 柱混凝土2-1 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 61 | 柱混凝土2-2 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 62 | 柱混凝土2-3 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 63 | 柱混凝土2-4 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 64 | 柱混凝土2-5 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 65 | 柱混凝土3-1 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 66 | 柱混凝土3-2 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 67 | 柱混凝土3-3 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 68 | 柱混凝土3-4 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 69 | 柱混凝土3-5 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 70 | 梁板钢筋1-1 |
3天 | 2017-09-01 | 2017-09-03 | ||
| 71 | 梁板钢筋1-2 |
3天 | 2017-09-01 | 2017-09-03 | ||
| 72 | 梁板钢筋1-3 |
3天 | 2017-09-01 | 2017-09-03 | ||
| 73 | 梁板钢筋1-4 |
3天 | 2017-09-01 | 2017-09-03 | ||
| 74 | 梁板钢筋1-5 |
3天 | 2017-09-01 | 2017-09-03 | ||
| 75 | 梁板钢筋2-1 |
3天 | 2017-09-01 | 2017-09-03 | ||
| 76 | 梁板钢筋2-2 |
3天 | 2017-09-01 | 2017-09-03 | ||
| 77 | 梁板钢筋2-3 |
3天 | 2017-09-01 | 2017-09-03 | ||
| 78 | 梁板钢筋2-4 |
3天 | 2017-09-01 | 2017-09-03 | ||
| 79 | 梁板钢筋2-5 |
3天 | 2017-09-01 | 2017-09-03 | ||
| 80 | 梁板钢筋3-1 |
3天 | 2017-09-01 | 2017-09-03 | ||
| 81 | 梁板钢筋3-2 |
3天 | 2017-09-01 | 2017-09-03 | ||
| 82 | 梁板钢筋3-3 |
3天 | 2017-09-01 | 2017-09-03 | ||
| 83 | 梁板钢筋3-4 |
3天 | 2017-09-01 | 2017-09-03 | ||
| 84 | 梁板钢筋3-5 |
3天 | 2017-09-01 | 2017-09-03 | ||
| 85 | 梁板混凝土1-1 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 86 | 梁板混凝土1-2 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 87 | 梁板混凝土1-3 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 88 | 梁板混凝土1-4 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 89 | 梁板混凝土1-5 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 90 | 梁板混凝土2-1 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 91 | 梁板混凝土2-2 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 92 | 梁板混凝土2-3 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 93 | 梁板混凝土2-4 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 94 | 梁板混凝土2-5 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 95 | 梁板混凝土3-1 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 96 | 梁板混凝土3-2 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 97 | 梁板混凝土3-3 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 98 | 梁板混凝土3-4 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 99 | 梁板混凝土3-5 |
1天 | 2017-09-01 | 2017-09-01 | ||
| 100 | 柱梁板模板拆除1-1 |
4天 | 2017-09-01 | 2017-09-04 | ||
| 101 | 柱梁板模板拆除1-2 |
4天 | 2017-09-01 | 2017-09-04 | ||
| 102 | 柱梁板模板拆除1-3 |
4天 | 2017-09-01 | 2017-09-04 | ||
| 103 | 柱梁板模板拆除1-4 |
4天 | 2017-09-01 | 2017-09-04 | ||
| 104 | 柱梁板模板拆除1-5 |
4天 | 2017-09-01 | 2017-09-04 | ||
| 105 | 柱梁板模板拆除2-1 |
4天 | 2017-09-01 | 2017-09-04 | ||
| 106 | 柱梁板模板拆除2-2 |
4天 | 2017-09-01 | 2017-09-04 | ||
| 107 | 柱梁板模板拆除2-3 |
4天 | 2017-09-01 | 2017-09-04 | ||
| 108 | 柱梁板模板拆除2-4 |
4天 | 2017-09-01 | 2017-09-04 | ||
| 109 | 柱梁板模板拆除2-5 |
4天 | 2017-09-01 | 2017-09-04 | ||
| 110 | 柱梁板模板拆除3-1 |
4天 | 2017-09-01 | 2017-09-04 | ||
| 111 | 柱梁板模板拆除3-2 |
4天 | 2017-09-01 | 2017-09-04 | ||
| 112 | 柱梁板模板拆除3-3 |
4天 | 2017-09-01 | 2017-09-04 | ||
| 113 | 柱梁板模板拆除3-4 |
4天 | 2017-09-01 | 2017-09-04 | ||
| 114 | 柱梁板模板拆除3-5 |
4天 | 2017-09-01 | 2017-09-04 | ||
| 115 | 脚手架安装1 |
2天 | 2017-09-01 | 2017-09-02 | ||
| 116 | 脚手架安装2 |
2天 | 2017-09-01 | 2017-09-02 | ||
| 117 | 脚手架安装3 |
2天 | 2017-09-01 | 2017-09-02 | ||
| 118 | 脚手架拆除1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 119 | 脚手架拆除2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 120 | 脚手架拆除3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 121 | 砌砖墙1-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 122 | 砌砖墙1-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 123 | 砌砖墙1-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 124 | 砌砖墙1-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 125 | 砌砖墙1-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 126 | 砌砖墙2-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 127 | 砌砖墙2-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 128 | 砌砖墙2-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 129 | 砌砖墙2-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 130 | 砌砖墙2-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 131 | 砌砖墙3-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 132 | 砌砖墙3-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 133 | 砌砖墙3-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 134 | 砌砖墙3-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 135 | 砌砖墙3-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 136 | 屋面找平层1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 137 | 屋面找平层2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 138 | 屋面找平层3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 139 | 屋面防水层1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 140 | 屋面防水层2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 141 | 屋面防水层3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 142 | 屋面挤塑板隔热层1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 143 | 屋面挤塑板隔热层2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 144 | 屋面挤塑板隔热层3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 145 | 屋面保护层1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 146 | 屋面保护层2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 147 | 屋面保护层3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 148 | 外墙面砖1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 149 | 外墙面砖2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 150 | 外墙面砖3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 151 | 内墙天棚抹灰1-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 152 | 内墙天棚抹灰1-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 153 | 内墙天棚抹灰1-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 154 | 内墙天棚抹灰1-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 155 | 内墙天棚抹灰1-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 156 | 内墙天棚抹灰2-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 157 | 内墙天棚抹灰2-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 158 | 内墙天棚抹灰2-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 159 | 内墙天棚抹灰2-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 160 | 内墙天棚抹灰2-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 161 | 内墙天棚抹灰3-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 162 | 内墙天棚抹灰3-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 163 | 内墙天棚抹灰3-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 164 | 内墙天棚抹灰3-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 165 | 内墙天棚抹灰3-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 166 | 内墙天棚涂料1-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 167 | 内墙天棚涂料1-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 168 | 内墙天棚涂料1-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 169 | 内墙天棚涂料1-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 170 | 内墙天棚涂料1-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 171 | 内墙天棚涂料2-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 172 | 内墙天棚涂料2-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 173 | 内墙天棚涂料2-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 174 | 内墙天棚涂料2-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 175 | 内墙天棚涂料2-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 176 | 内墙天棚涂料3-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 177 | 内墙天棚涂料3-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 178 | 内墙天棚涂料3-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 179 | 内墙天棚涂料3-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 180 | 内墙天棚涂料3-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 181 | 地面垫层1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 182 | 地面垫层2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 183 | 地面垫层3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 184 | 地面装饰1-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 185 | 地面装饰1-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 186 | 地面装饰1-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 187 | 地面装饰1-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 188 | 地面装饰1-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 189 | 地面装饰2-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 190 | 地面装饰2-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 191 | 地面装饰2-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 192 | 地面装饰2-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 193 | 地面装饰2-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 194 | 地面装饰3-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 195 | 地面装饰3-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 196 | 地面装饰3-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 197 | 地面装饰3-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 198 | 地面装饰3-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 199 | 安装门窗框1-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 200 | 安装门窗框1-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 201 | 安装门窗框1-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 202 | 安装门窗框1-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 203 | 安装门窗框1-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 204 | 安装门窗框2-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 205 | 安装门窗框2-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 206 | 安装门窗框2-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 207 | 安装门窗框2-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 208 | 安装门窗框2-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 209 | 安装门窗框3-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 210 | 安装门窗框3-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 211 | 安装门窗框3-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 212 | 安装门窗框3-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 213 | 安装门窗框3-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 214 | 安装门窗扇1-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 215 | 安装门窗扇1-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 216 | 安装门窗扇1-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 217 | 安装门窗扇1-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 218 | 安装门窗扇1-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 219 | 安装门窗扇2-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 220 | 安装门窗扇2-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 221 | 安装门窗扇2-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 222 | 安装门窗扇2-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 223 | 安装门窗扇2-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 224 | 安装门窗扇3-1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 225 | 安装门窗扇3-2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 226 | 安装门窗扇3-3 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 227 | 安装门窗扇3-4 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 228 | 安装门窗扇3-5 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 229 | 明沟1 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 230 | 明沟2 |
5天 | 2017-09-01 | 2017-09-05 | ||
| 231 | 明沟3 |
5天 | 2017-09-01 | 2017-09-05 |